South Franks Avenue Project

The County Road Commission is overseeing a paving project on South Franks Avenue between US-12 and Fawn River Road. The road will remain open to traffic during the project, but traffic will be slowed as flaggers are used to stop, start, and direct vehicles as lanes are opened and closed. We have supplied the Road Commission with our school start and end times in an effort to reduce the impact to arrival and dismissal. Having said this, we anticipate that pick up and drop off routines will be slowed during the duration of the project.

Anticipated schedule (subject to change based on weather and other factors):
Initial Traffic Set Up 9/6/22 through 9/9/22
Milling Operations 9/9/22 through 9/12/22
Paving Operations 9/12/22 through 9/14/22
Shoulder Gravel 9/19/22 through 9/23/22
Pavement Markings 9/26/22 through 9/30/22
Project Clean up 10/3/22 through 10/7/22


La Comisión de Carreteras del Condado está supervisando un proyecto de pavimentación en South Franks Ave. entre US-12 y Fawn River Road. La carretera permanecerá abierta al tráfico durante el proyecto, pero se reducirá la velocidad del tráfico ya que se utilizan banderilleros para detener, arrancar y dirigir los vehículos a medida que se abren y cierran los carriles. Le hemos proporcionado a la Comisión de Carreteras nuestros horarios de inicio y finalización de la escuela en un esfuerzo por reducir el impacto de la llegada y la salida. Habiendo dicho esto, anticipamos que las rutinas de recoger y dejar se reducirán durante la duración del proyecto.

Horario anticipado (sujeto a cambios según el clima y otros factores):
Configuración de tráfico inicial del 6/9/22 al 9/9/22
Operaciones de fresado del 9/9/22 al 12/9/22
Operaciones de pavimentación del 12/09/22 al 14/09/22
Hombro Grava 19/09/22 hasta 23/09/22
Marcas en el pavimento 26/09/22 hasta 30/09/22
Limpieza del proyecto del 3/10/22 al 7/10/22